December 20, 2017

The following work will be taking place through to the end of Phase 1 of the project (early 2018):

    • Crews working from 7 a.m. to 10:30 p.m.
    • Construction of exoskeleton ongoing
    • Installation of temporary heating ongoing
    • Installation of temporary electrical system ongoing
    • Repairs to portico foundations going 
    • Footing and draining tile installation
    • Burlap wetting on exposed foundation wall
    • Decking installation 
    • Pedestrian access from Richmond to Grafton is on the east side of Province House
    • Weekly inspection of job site by the Joint Health and Safety Committee
    • Site clean up