Current Twinning (Phase IIIB)
Construction timeline, 2009-2014
Phase IIIB –1 (9 km section east of Lake Louise):
Completed in September 2009
- Paving (July 2009)
- Two 60 m wildlife overpasses (Sept 2009)
- Landscaping (Sept 2009)
Phase IIIB – 2 (14 km section west of Castle Junction):
- Median separated lanes (2009)
- Guiderail separated lanes (1010)
- 18 m wildlife underpass (2009-2010)
- Two 60 m wildlife overpasses (2009-2010)
- Overlay lanes (2011)
- Landscaping (2011)
Phase IIIB-3 (8.5 km section from Lake Louise west to the Alberta/BC border):
- Reconfigure Icefields Parkway interchange (2009-2011)
- New eastbound Bow River Bridge (2009-2011)
- Highway twinning (2009-2012)
- New CP Rail bridge (2010 – 2013)
- New Bath Creek bridge (2010-2013)
- 60 m wildlife underpass (2010-2013)
- Overlay lanes (2014)
- Landscaping (2014)
An overview of the Trans-Canada Highway Twinning Project: Phase IIIB near Lake Louise, Alberta© Parks Canada