Trans-Canada Highway Twinning

Table of Contents | Introduction | Current Twinning | Highway Fencing & Wildlife Crossings

Current Twinning (Phase IIIB)

Construction timeline, 2011-2013

Phase IIIB –1 (9 km section east of Lake Louise):
Completed in September 2009

Phase IIIB – 2 (14 km section west of Castle Junction):

  • Mannix Pit Rehabilitation (2012)
  • Landscaping (2012)

Phase IIIB-3 (8.5 km section from Lake Louise west to the Alberta/BC border):

  • Pedestrian Overpass (2011-2012)
  • New highway lanes (2011-2012)
  • Two new highway bridges (2011-2012)
  • Three wildlife underpasses (2011-2012)
  • Overlay lanes/Landscaping (2013)
 Trans-Canada Highway Twinning Project: Phase IIIB  
An overview of the Trans-Canada Highway Twinning Project: Phase IIIB near Lake Louise, Alberta