Parks Canada
Symbol of the Government of Canada

Internal Audit and Evaluation Documents

Parks Canada - Parks Canada Performance, Evaluation and Audit 2006 - 2009 Plan

Report tabled and approved by the Audit Committee and the Evaluation Committee

[ Previous | Table of Contents ]


List of Tables

Table 1: Planned Spending for 2008-2009
Table 2: Internal Audit Projects Carried forward from 2007-2008
Table 3: Evaluation Projects Carried Forward From 2007-2008

Table 4: MAF Universe and Scheduled Audit Projects for 2008-2009 and 2009-2010

Table 5: Internal Audit Project Scheduling for 2008-2009

Table 6: PAA Universe and Five-Year Evaluation Schedule

Table 7: Evaluation Project Scheduling for 2008-2009
Table 8: 2008-2009 Capacity For Internal Audit and Evaluation
Table 9: Comparison of 2008 and 2007 MAF Universe Elements and Links to Draft Core Management Controls
Table 10: Comparison of 2008 and 2007 PAA Universe Elements
Table 11: Comparison of MAF 2007 and 2008 Ratings
Table 12: Results of 2008 MAF Assessement
Table 13: Comparison of PAA 2007 and 2008 Ratings
Table 14: Result of 2008 PAA Assessment

Table 1: Planned Spending for 2008-2009

 

CAEE Office

Internal Audit

Evaluation

Total

FTEs

2

6

3

11

Salary

36,297

433,390

215,383

685,070

Benefits

7,259

86,678

43,077

137,014

Accommodations

4,719

56,341

28,000

89,059

Sub Total

48,275

576,408

286,459

911,143

O&M For Staff Support

12,500

37,500

18,750

68,750

O&M for Professional Services

17,637

156,559

243,418

417,614

Auditor Training and Certification Funds

 

30,000

 

30,000

Audit Committee Funds

135,000

 

 

135,000

Sub Total O&M

165,137

224,059

262,168

651,364

Grand Total

213,412

800,467

548,627

1,562,506

The FTE for the CAEE is included in the table but not the salary, and associated benefit and accommodations costs, which are administered centrally for all executive level employees in the Agency. Table does not include carry forward amounts from 2007-2008 that were not yet allocated.

Table 2: Internal Audit Projects Carried forward from 2007-2008

Topic

Type

Description

Planned or Actual Dates

Comments

Planned 2007-08

Start Date

Completion of the fieldwork

Completion of Report

Date of Approval by Committee**

National Level Finance & Administrative Management Control Framework

Description and survey*

Develop description and survey of the corporate management control framework for finance & administration

Y

Jan 08

May 08

June 08

Sept 08

This project was delayed by approximately 7 months in order to respond to other unplanned projects requested by management

Financial and Administrative Controls

Assurance

Audits related to contracting, travel claims; accounts payable, revenue, inventory, and financial coding

           

National Parks Directorate

Y

Dec 07

Feb 08

Jan 08

Sept 08

DG East

Y

Oct 07

Nov 07

April 08

Sept 08

Offices of DG North & West

Y

Nov 07

Dec 07

May 08

Sept 08

Information Technology / Information system

Description and Survey

Develop description and survey of major IT governance, risks and controls related to systems, information continuity, system application controls/security, system integration and systems under development

Y

April 08

Oct. 08

Dec. 08

March 09

Project completion is delayed approximately 1 year due to taking substantial more time than anticipated to develop and award a contract to complete the work (i.e., not awarded until March 2008).

Information Management and Privacy

Description and Survey

Description and survey of information management and privacy governance, risks and controls

Y

June 08

Nov 08

Jan 08

March 09

Project completion is delayed approximately 1 year. Originally it was expected that this project would be combined with the IT/IS project. Due to the scope and scale of that project it was decided to postpone the IM component until 2008-2009.

Follow-up Audits

Follow-up

Follow up audit on progress in implementation of management responses to the finance and administrative management audit of Northern Ontario FU.

Y

Dec 07

March 08

May 08

Sept 08

The fieldwork scheduled for January 08 was postponed to March 08 to accommodate field unit operations. Changes in field unit management have delayed the final debriefing on audit results until end of May, 2008

Overtime Expenditures

Description and Survey

Initiated in response to risks identified by AG.

N

Dec. 08

Feb. 08

May 08

Sept 08

The project was not scheduled in the 2007-2008 Plan but will be delivered on time.

* Description and survey refers to documenting governance, controls and risk management mechanisms related to the element in order to identify future areas within the element for audit work
** Approval dates by the internal audit committee are tentative, as the new external committee has not yet met to plan its Agenda for the year

Table 3: Evaluation Projects Carried Forward From 2007-2008

Topic

Type

Description

Planned or Actual Dates

Comments

Planned 2007-08

Start Date

Completion of the fieldwork

Completion of Report

Date of Approval by Committee

Asset Management and Capital Investment Program

Evaluation

This evaluation focuses on whether relevant assets are acquired and maintained and whether performance with respect to investment, compliance regimes and other program goals are met.

Y

May 06

March 08

June 08

Sept 08

The project has been delayed by six months as a result of difficulties in obtaining and reconciling key information on the number, value and condition of assets and in documenting prioritization and planning process.

Through Highways Management

Description and Framework*

A description of the framework and objectives for highway management and the systems in place to monitor relevance and performance as a basis for identifying future evaluation work.

Y

Jan 08

Sept 08

Nov 08

Jan. 09

The project is delayed by six months as a result of delays to the asset management project and to respond to management requests to focus on other evaluation work.

Learning Strategy Evaluation Framework

Description and Framework

A description of the Agency's learning strategy and objectives with a plan to evaluate objective achievement in the long term.

Y

Jan 07

Oct 08

Nov 08

Sept 08

The report was tabled December 12th 07 for approval but sent back for revisions and review by the Agency Human Resource Committee prior to re-tabling. Currently the Agency is in the process of developing a new learning policy and guidelines and developing a performance framework and HR dashboard that will include elements related to learning. Farther work on this project is postponed until these elements of the framework are in place.

* Description and framework refers to describing the elements of a program or sub activity, its logic and systems for monitoring relevance and performance to support future evaluation projects.

Table 4: MAF Universe and Scheduled Audit Projects for 2008-2009 and 2009-2010

 

Rated Elements

Core Controls

2008-2009

2009-2010

Values and Ethics

Values Based Leadership

PSV-1 to 5

Audit

 

Governance

Corporate Performance Framework

G-3

   

Effective Corporate Management Structures

G-1, 2, 5, 6

   

Organizational Structure and Accountability,

AC-1 to 3

   

Management Planning and Public Consultation

G-4, 5

   

Business Planning

G-4

   

Collaborative Arrangements and Managing With Others

AC-4

Description and Survey

Audit

Policies and Programs

Analysis to support policy and program design

PP-1 to 3

   

Performance and Results

Performance/results

RP 1 to 3

   

Management of Change

Management of change, knowledge and talent management

PPL-6, LICM-1-4

 

Description and Survey

Risk Management

Risk Management Policies and Practices

RM-1 to 8

 

Review Level Work

People

Sustainable HR Policies and HR Planning

PPL-1, 7

Description and Survey

 

Classification, Recruitment, Hiring and Promotion

PPL-2, 3

   

Occupational Health and Safety

     

Individual Performance

PPL-5 RP-4

   

Internal Communications

PPL-8

   

Official Languages (Internal And External Service Delivery)

     

Labour Relations/Conflict Resolution

     

Stewardship

Information Management and Privacy

 

Description and Survey

Audit

Systems under development

ST-21

Description and Survey

 

Systems and information continuity

ST-19

 

System application controls/security

ST-11

 

New System Integration/Connectivity

   

Asset Management

ST-8, 9

Fleet Vehicle /Vessel Audit

 

Project Management

     

Realty Services (Land Management)

     

Security and Business Continuity

   

Description and Survey

Transfer Payments

     

Pay and Benefits Administration

 

Description and Survey Overtime System

Follow-up of Pay and Benefits Audit (including overtime)

Financial Planning and Budgeting

ST-1 to 4

Description and Survey National Level Management Control Framework

Financial and Administrative Control Audits

  • Fire Management Emergency Funds
  • National Level Revenue Management
  • West Quebec FU Follow-up Audit

Financial Management Policies

ST-5, 6

Transaction Processing

ST-10, 12, 13

Financial Monitoring

ST-14, 16-17, 20

Financial Reporting

ST-18, 20

Contract Management

ST-22

Other Expenditures (Hospitality, Travel, Taxis, Vehicle Rentals, AMEX, Conferences, Memberships)

 

Fees i.e., entry, camping, recreational services

 

Other Revenue

 

Table 5: Internal Audit Project Scheduling for 2008-2009

Projects

Planned or Actual Dates

Resources Required*
2008-2009

Project

Type

Description

Carry Forward from 2007-08

Start Date

Completion of the fieldwork

Completion of Report

Tabling at Audit Committee

Approximate hours

O&M

Value and Ethics

Assurance

Examining the Agency's policies and procedures to assess the effectiveness of core controls related to values and ethics to support the external audit committee in its oversight responsibilities.

N

Dec. 08

Feb 09

March 09

April 09

400

 

Collaborative Arrangements and Managing with Others

Description and survey

Document the types and range of the collaborative arrangements within the Agency and associated risks in controls to assist in planning future audit work

Y

June 08

 

March 09

April 09

600

$5K

Sustainable HR Policies And HR Planning

Description and Survey

Document HR policies, plans and processes assess alignment with strategic plan and business plans, mechanisms for assessing compliance and renewing policies and plans.

Y

Dec. 08

 

May 09

Sept 09

600

 

Information Management and Privacy

Description and Survey

Document information management and privacy governance, risks and controls to plan future audit work

Y

June 08

Dec 08

March 09

April 09

700

 

Information Technology / Information system

Description and Survey

Document major IT governance, risks and controls related to systems, information continuity, system application controls/security, system integration and systems under development. A risk-based audit plan is to be delivered.

Y

April 08

Sept 08

Dec 08

Jan. 09

1100

$140K

Fleet Vehicle/Vessel Management

Assurance

As a result of audits of financial controls it was decided to conduct assurance work on the controls and practices related to Parks Canada's fleet estimated to include over 1600 vehicles and vessels with an approximate value of $36M.

N

April 08

Sept 08

Dec 08

Jan. 09

1100

$25K

National Level Finance & Administrative Management Control Framework

Description and Survey

Document the corporate management control framework for finance & administration processes to assist in providing an annual holistic opinion on the state of governance, risk management and control and to help identify future audit projects

Y

Jan 08

May 08

June 08

Sept 08

100

 

Financial and Administrative Control Audits

Assurance

Revenue Management
Based on its findings of previous field unit level finance and administrative audits it is proposed to conduct a national level audit of revenue management focusing on risks related to cash management and segregation of duties to ensure the completeness and accuracy of data.

Y

June 08

Dec 08

March 09

April 09

1100

$25K

Fire Management Emergency Funds
The National Parks Act mandates the Agency to provide fire protection in the national parks for structural and wildfires. Over the years, Parks' financial constraints requested supplementary funding from TB to cover the costs of the program. This project is conducted as a routine audit required by the TB Submission.

Y

April 08

Sept 08

Dec 08

Jan 09

1100

$5-10K

Follow up Audit
Follow up audit on progress in implementation of management responses to the financial and administrative audit of Western Quebec FU.

N

Aug 08

Sept 08

Dec 08

Jan 09

400

$3K

* Approximate hours reflect required effort within the fiscal year. Projects that extend beyond a fiscal year will require more effort than shown in the table. Staff or consultants may perform the work. O&M required includes costs of professional services and/or costs of staff travel.

Table 6: PAA Universe and Five-Year Evaluation Schedule

Sub Activities and Sub Sub-Activities (indented)

Expenditures 2006-2007
(000)

2008-2009

2009-2010

2010-2011

2011-2012

2012-2013

Heritage Places Establishment

20,489

         

National Park Establishment and Expansion

14,239

 
Description and Framework
 
Evaluation
 

National Historic Sites Designation (Persons, Places, Events)

4,753

         

National Marine Conservation Area Establishment

82

       
Description and Framework
 

Other Heritage Places Designations

1,415

         

Heritage Resources Conservation

193,989

         

National Parks Conservation

126,985

 
Description and Framework
 
Evaluation
   

Species at Risk

National Historic Sites Conservation

49,763

   
Description and Framework
 
Evaluation

National Marine Conservations Areas Sustainability

1,466

       
Description and Framework
 

Other Heritage Places Conservation

15,775

         

National Historic Sites Cost-Sharing

Evaluation

Commercial Heritage Properties Incentive Fund

 

Historic Places Initiative

Public Appreciation and Understanding

39,643

         

Outreach Education and Agency Communications

 

   
Description and Framework
   

Engagement

 

       

Visitor Experience

253,506

         

Marketing and Promotion

14,316

     
Description and Framework
   

National Parks Interpretation

24,884

     
Description and Framework
Evaluation

National Historic Sites Interpretation

43,902

     

National Marine Conservation Areas Interpretation

943

     

National Parks Visitor Activities and Services

116,884

 
Description and Framework
Evaluation
     

Public Safety

National Historic Sites Visitor Activities and Services

51,606

       

National Marine Conservation Areas Visitor Activities and Services

972

       

Town-Site and Throughway Infrastructure

96,986

         

Townsite Management

12,715

         

Through Highways Management

75,145

Description and Framework
Evaluation
     

Through Waterways Management

9,125

         
The General Class Contribution Program, which is not specific to one program activity or sub-activity, is to be evaluated in 2010-2011

Table 7: Evaluation Project Scheduling for 2008-2009

Topic

Type

Description

Planned or Actual Dates

Resources Required* 2008-2009

Planned 2007-08

Start Date

Completion of the fieldwork

Completion of Report

Date of Approval by Committee

Approximate hours

O&M

Asset Management and Capital Investment Program

Evaluation

This evaluation focuses on whether relevant assets are acquired and maintained and whether performance with respect to investment, compliance regimes and other program goals are met.

Y

May 06

March 08

June 08

Sept 08

100

 

Through Highways Management

Description and Framework

A description of the program sub-activity and objectives for and the systems in place to monitor relevance and performance as a basis for a subsequent evaluation.

Y

Jan 08

Sept 08

Nov 08

Jan. 09

800

$25K

Visitor Activities and Services

Description and Framework

A description of the program sub-activity and objectives and the systems in place to monitor relevance and performance as a basis for a subsequent evaluation

N

June 08

March 09

June 09

Sept 09

2600

$150K

* Approximate hours reflect required effort. Projects that extend beyond a fiscal year will require more effort than shown in the table. Staff or consultants may perform the work. O&M required includes costs of professional services and/or costs of staff travel.

Table 8: 2008-2009 Capacity For Internal Audit and Evaluation

A) Resources

CAEE Office

Internal Audit

Evaluation

Total

FTEs

2

6

3

11

Hours Available for Work (Less vacation, sick and training days, leaving 1,725 hours per FTE)

3,450

10,350

5,175

18,975

Professional Service Hours Purchased (O&M for professional Services/$160 per hour)

110

978

1,521

2,610

Total Hours Available

3,560

11,328

6,696

21,585

B) Demands

Administration i.e., (70% of CAEE, 100% of Admin. Assistant and 30% of other staff hours are allocated for activities such as planning, meetings, work on internal systems, support to the audit and evaluation committee, training, breaks and general down time

-2,933

-3,399

-2,009

-6,267

OCG/TBS Directed Audits or Evaluations (25% of one FTE)

 

-430

-430

-860

Follow up from previous years (10% of one FTE)

 

-175

-175

-350

Special Requests

 

-400

-400

-800

Consulting/Advice/Coordination (35% of one FTE)

 

-600

-600

-1,200

Residual Hours for Risk Based Projects

*

6,638

3,395

10,033

C) Project Capacity

Number of Typical Projects: (Internal Audit=1200 hours per project, Evaluation=2200 hours per project)

 

5.5

1.5

 

* Approximately 626 hours of project capacity in CAEE's Office were assigned equally to audit and evaluation.

Table 9: Comparison of 2008 and 2007 MAF Universe Elements and Links to Draft Core Management Controls

Order

Major MAF Element

Element in MAF 5 TBS Assessment

Rated Elements

Order in 2007 Universe

Link to Core Management Control Guide for Auditors

1

Public Service Values

1

Values Based Leadership, values and ethics are established, understood, communicated, effective and monitored

19

PSV-1 to 5

2

Governance

2

Corporate Performance Framework (Consistency of strategic objective and PAA with mandate, clarity and measurability of outcomes, alignment of PAA with outcomes)

2, 13

G-3

3

3

Effective Corporate Management Structures (e.g., Ex. Board, Finance and HR Committees, Min Roundtable, other governance mechanisms)

1

G-1, 2, 5, 6

4

3

Organizational Structure and Accountability, Authority, Responsibility - Clear, Communicated And Understood

14, 15

AC-1 to 3

5

3

Management Planning And Public Consultation (Integration with corporate planning, enables effective allocation of resources, alignment of activities to outcomes, clarity of results and management of accountabilities)

4

G-4, 5

6

3

Business Planning: Integration with corporate and management planning, resource allocation to achieve results, clarity of results, adequate financial and non-financial information).

5,6,8

G-4

7

3

Collaborative Arrangements And Managing With Others (Engagement of Third Parties in Delivery of Mandate)

9-11

AC-4

8

Policy and Programs

5

Analysis to support policy and program design: Quality, adequacy, soundness of analysis, resourcing, approach for monitoring

16-17

PP-1 to 3

9

Results and Performance

7

Performance/results: at the organizational/program level tracked/monitored against expectations, reported, corrective action taken

12

RP 1 to 3

10

Change Management

8

Management of change, knowledge and talent management, developing employee skills and rewards and sanctions

23

PPL-6, LICM-1-4

11

Risk Management

9

Risk Management Policies And Practices (Risk management process and risk mitigation strategies established, Informs the Corporate Plan, Formally Articulated)

18

RM-1 to 8

12

People

10, 11, 21

Sustainable HR Policies And HR Planning, aligned, integrated with other planning

20

PPL-1, 7

13

Classification, Recruitment, Hiring and Promotion, Design and Fairness

21

PPL-2, 3

14

Occupational Health And Safety

22

 

15

Individual Performance Linked to business performance, assessment of individual performance, performance linked to staff evaluations

24

PPL-5 RP-4

16

Internal Communications

25

PPL-8

17

Official Languages (Internal And External Service Delivery)

26

 

18

Labour Relations/Conflict Resolution

27

 

19

Stewardship

12

Information Management And Privacy (Governance, management of information; Administration/Compliance Privacy Act and ATIP)

28

 

20

13

Systems under development

29

ST-21

21

Systems and information continuity

30

ST-19

22

System application controls/security

31

ST-11

23

New System Integration/Connectivity

32

 

24

14

Asset Management

33

ST-8, 9

25

15

Project Management

NA

 

26

14

Realty Services (Land Management)

35

 

27

19

Security and Business Continuity

34, 36

 

28

 

Transfer Payments

37

 

29

 

Pay And Benefits Administration

38

 

30

17

Financial Planning and Budgeting (Budgets linked to objectives, clear process, timely allocation, challenge to assumptions, monitoring forecasts

40, 41

ST-1 to 4

31

Financial Management Policies (Established, communicated, compliance, monitored)

43, 44

ST-5, 6

32

Transaction Processing (Recording is accurate, timely, information is maintained, safeguarded, backed-up, adequate segregation of duties)

45, 47, 48

ST-10, 12, 13

33

Monitoring (Verification of assets and records, analysis of variance, comparison of results achieved against expectations, reallocation of resources)

46

ST-14, 16, 17, 20

34

Reporting (Financial information reviewed, approved, communicated internally and externally)

 

ST-18, 20

35

16

Contract Management

49

ST-22

36

 

Other Expenditures (Hospitality, Travel, Taxis, Vehicle Rentals, AMEX, Conferences, Memberships)

50-56

 

37

 

Revenue From Fees i.e., entry, camping, recreational services

57

 

38

 

Other Revenue: Staff housing, Business Licenses, Other Rights and Privileges

58-60

 

Table 10: Comparison of 2008 and 2007 PAA Universe Elements

Rated Elements

2006-2007 Expenditures
(000)

Modified 2007 Universe Page 16-17 of Plan

Original 2007 Universe Page 25 of Plan

 

Heritage Places Establishment

20,489

   

1

National Park Establishment and Expansion

14,239

1

1-2

2

National Historic Sites Designation (Persons, Places, Events)

4,753

2

3

3

National Marine Conservation Area Establishment

82

6

1

4

Other Heritage Places Designations

1,415

5

4

 

Heritage Resources Conservation

193,989

   

5

National Parks Conservation

126,985

3

5-10

6

Species at Risk

 

   

7

National Historic Sites Conservation

49,763

4

11-13

8

National Marine Conservations Areas Sustainability

1,466

6

5-10

9

Other Heritage Places Conservation

15,775

5

14

10

National Historic Sites Cost-Sharing

 

   

11

Commercial Heritage Properties Incentive Fund

 

   

12

Historic Places Initiative

 

   
 

Public Appreciation and Understanding

39,643

   

13

Outreach Education and Agency Communications

 

11

15-16

14

Engagement

 

 

Visitor Experience

253,506

   

15

Marketing and Promotion

14,316

7

17-18

16

National Parks Interpretation

24,884

8

22

17

National Parks Visitor Activities and Services

43,902

19-21

18

Public Safety

943

9

23

19

National Historic Sites Interpretation

116,884

10

22

20

National Historic Sites Visitor Activities and Services

 

19-21

21

National Marine Conservation Areas Interpretation

51,606

6

22

22

National Marine Conservation Areas Visitor Activities and Services

972

19-21

 

Town-Site and Throughway Infrastructure

96,986

   

23

Townsite Management

12,715

12

24-25

24

Through Highways Management

75,145

13

26

25

Through Waterways Management

9,125

14

27

Table 11: Comparison of MAF 2007 and 2008 Ratings

#

Sub Element

2007 Assessment Priority (0-10)

2008 Assessment Priority (-2 to +2)

N

Average Rating

13

Risk Management Policies and Practices

7.14

16

-0.78

27

Asset Management

8.57

13

-0.48

7

Collaborative Arrangements and Managing With Others

6.19

19.25

-0.27

21

Information Management and Privacy

6.67

14

-0.27

26

New System Integration/Connectivity

4.76

7

-0.14

28

Project Management

NA

10

-0.10

12

Management Of Change, Knowledge and Talent Management,

5.24

17

-0.07

23

Systems Under Development

5.71

8

-0.03

14

Sustainable HR Policies and HR Planning

6.19

14.75

0.12

30

Security And Business Continuity

5.00

7

0.14

46

Contract Management

8.1

17

0.19

29

Realty Services (Land Management)

5.24

10

0.23

9

Analysis to Support Policy and Program Design

6.67

13.75

0.24

25

System Application Controls/Security

4.76

6

0.33

5

Management Planning and Public Consultation

3.33

16.5

0.35

41

Financial Monitoring

4.29

15

0.52

4

Organizational Structure and Accountability,

3.81

17

0.57

51

Other Revenue: Staff Housing, Business Licences, Other Rights and Privileges

1.74

9

0.58

1

Values Based Leadership,

4.76

19.5

0.62

24

Systems and Information Continuity

5.71

6

0.63

34

Financial Planning, Budgeting, Forecasting

3.8

16

0.66

11

Performance Tracking, Reporting, Responding

9.52

18.75

0.69

15

Classification, Recruitment, Hiring And Promotion

5.71

16.5

0.74

49

Other Revenue

4.13

16

0.77

18

Internal Communications

3.81

14.25

0.79

3

Effective Corporate Management Structures

4.76

16.25

0.85

6

Business Planning

4.28

18

0.85

17

Individual Performance Assessment

4.76

13.5

0.89

50

Revenue From Fees

8.57

11

1.00

19

Official Languages (Internal And External Service Delivery)

2.86

15.75

1.03

32

Pay and Benefits Administration

2.86

13

1.04

45

Financial Reporting

NA

18

1.08

38

Financial Transaction Processing

3.01

16

1.13

2

Corporate Performance Framework

2.62

18.75

1.20

31

Transfer Payments

2.86

6

1.21

36

Financial Management Policies

3.1

17

1.21

20

Labour Relations/Conflict Resolution

1.43

12.75

1.22

16

Occupational Health and Safety

5.71

15

1.33

Table 12: Results of 2008 MAF Assessement

(Average score per respondent across four questions for each element)

Table 12: Results of 2008 MAF Assessement
Click to enlarge

Table 13: Comparison of PAA 2007 and 2008 Ratings

#

Program Activities

2006-2007 Expenditures

2007 Assessment Priority (0-10)

2008 Assessment Priority (-2 to +2)

Average

N

Rating

 

Heritage Places Establishment

20,488.60

     

1

National Park Establishment and Expansion

14,239.10

5.56

11

0.64

2

National Historic Sites Designation (Persons, Places, Events)

4,752.60

2.22

14.5

0.91

3

National Marine Conservation Area Establishment

82.00

6.11*

9.75

0.46

4

Other Heritage Places Designations

1,414.90

5.00*

14

0.43

 

Heritage Resources Conservation

193,989.20

     

5

National Parks Conservation

126,984.50

9.44

12.75

0.20

6

Species at Risk

   

10

0.60

7

National Historic Sites Conservation

49,763.40

6.81

17

0.41

8

National Marine Conservations Areas Sustainability

1,466.20

6.11*

7

-0.04

9

Other Heritage Places Conservation

15,775.10

5.00*

   

10

National Historic Sites Cost-Sharing

   

8

-0.09

11

Commercial Heritage Properties Incentive Fund

   

9

0.53

12

Historic Places Initiative

   

8.25

0.70

 

Public Appreciation and Understanding

39,643.00

     

13

Outreach Education and Agency Communications

 

4.44*

15.25

0.18

14

Engagement

 

13.25

0.17

 

Visitor Experience

253,506.40

     

15

Marketing and Promotion

14,316.10

6.67

13

0.35

16

National Parks Interpretation

24,883.80

6.11

11.75

0.87

17

National Parks Visitor Activities and Services

116,884.40

10.5

0.69

18

Public Safety

 

5.56

 

0.60

19

National Historic Sites Interpretation

43,901.50

5.56

11.75

0.50

20

National Historic Sites Visitor Activities and Services

51,605.90

10.5

0.50

21

National Marine Conservation Areas Interpretation

942.60

6.11

6

0.25

22

National Marine Conservation Areas Visitor Activities and Services

972.10

5

0.30

 

Town-Site and Throughway Infrastructure

96,985.60

     

23

Townsite Management

12,715.40

2.22

7

0.93

24

Through Highways Management

75,145.40

7.78

9

-0.06

25

Through Waterways Management

9,124.80

6.11

7

0.50

* Other heritage places establishment and conservation received one rating in 2007 that is shown separately against the two sub activities. Marine Conservation Area establishment, sustainability and visitor experience received one rating in 2007 shown against each sub-activity.
* Corporate Service costs are proportionally allocated to program activity based on fund centres.

Table 14: Result of 2008 PAA Assessment

(Average score per respondent across four questions)

Table 14: Result of 2008 PAA Assessment
Click to enlarge


[ Previous | Table of Contents ]